Gutenberg Solar

A 79.9 MW solar power plant in Northampton, North Carolina, owned by Dominion Energy Inc., commissioned in 2019.

Facility nameplate · EIA Plant ID 63076Solar
Nameplate capacity
79.9 MW
Primary fuel
Solar
Commissioned
2019
Time in queue (2015→2019)
4.4 yrs
Location
Northampton, North Carolina
Generation (2024)
152.9 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a PJM Interconnection interconnection request (LBNL Queued Up): queued 2015, commercial operation 2019 — 4.4 years in the queue. See the PJM queue or typical durations.

Location

Map of the United States showing the location of Gutenberg Solar

Northampton, North Carolina · 36.4864, -77.5348

Reported annual generation

YearGWh
201918
2020152.9
2021176
2022160.1
2023141
2024152.9

Nearby power plants

PlantFuelCapacityDistance
Pecan SolarSolar74.9 MW~5 km
Pleasant Hill PV1Solar20 MW~5 km
Garysburg SolarSolar5 MW~5 km
Hemlock SolarSolar5 MW~6 km
Seaboard Solar LLCSolar5 MW~6 km
Schell Solar FarmSolar5 MW~6 km

See all solar plants in North Carolina or browse all plants in North Carolina.