Roaring Brook, LLC

A 79.7 MW wind power plant in Lewis, New York, owned by Avangrid Power LLC, commissioned in 2021.

Facility nameplate · EIA Plant ID 61041Wind
Nameplate capacity
79.7 MW
Primary fuel
Wind
Commissioned
2021
Time in queue (2016→2022)
5.7 yrs
Location
Lewis, New York
Generation (2024)
163.1 GWh
Status
Operating
Technology
Onshore Wind Turbine
Units
1

This facility was matched to a NYISO interconnection request (LBNL Queued Up): queued 2016, commercial operation 2022 — 5.7 years in the queue. See the NYISO queue or typical durations.

Location

Map of the United States showing the location of Roaring Brook, LLC

Lewis, New York · 43.7096, -75.6162

Reported annual generation

YearGWh
202130.9
2022179.2
2023170.1
2024163.1

Nearby power plants

PlantFuelCapacityDistance
Maple Ridge Wind FarmWind321.2 MW~9 km
Martinsburg CSG LLCSolar2.2 MW~12 km
Chambers 3 - Lewis CountySolar2 MW~12 km
Number Three Wind ProjectWind106 MW~15 km
Copenhagen SolarSolar2.9 MW~19 km
Copenhagen PlantHydroelectric3.3 MW~21 km

See all wind plants in New York or browse all plants in New York.