State queue · Indiana
Indiana interconnection queue
300 proposed generation and storage projects — 289 active and 11 suspended — are in Indiana's interconnection queue, primarily in the MISO, totaling 59.60 GW of requested capacity. Solar leads with 23.34 GW.
300
Proposed projects
59.60 GW
Requested capacity
Solar
Largest resource type
2026
Median planned online year
Requested capacity by resource type
Solar 39.2%Gas 23.9%Battery 17.1%Solar + Battery 13.5%Wind 5.9%Other 0.4%
Proposed projects by resource type
Solar projects147 · 23.34 GWGas projects20 · 14.25 GWBattery projects66 · 10.17 GWSolar + Battery projects42 · 8.07 GWWind projects20 · 3.50 GW
Also in the queue (too few for a dedicated page): Other (5).
All proposed projects in Indiana
| Type | ||||
|---|---|---|---|---|
| Schahfer CCGTs E0042 | Gas | 2.74 GW | 2025 | 2028 |
| Queue J3999 J3999 | Gas | 1.54 GW | 2025 | 2030 |
| Malden CCGT E0035 | Gas | 1.09 GW | 2025 | 2028 |
| Replacing 1014.7 MW of coal generation with Gas/Steam; Cayuga CC1 CC2 R1044 | Gas | 1.04 GW | 2024 | 2028 |
| Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; Schahfer R5062 | Gas | 732.7 MW | 2024 | 2027 |
| Queue J351 J351 | Gas | 715 MW | 2014 | 2020 |
| Queue J2846 J2846 | Solar | 700 MW | 2022 | 2025 |
| Bluegrass Power LLC project AG2-072 | Gas | 700 MW | 2025 | 2026 |
| Queue AH2-348 AH2-348 | Solar | 700 MW | 2022 | 2025 |
| Queue J3604 J3604 | Gas | 650 MW | 2024 | 2027 |
| Queue J3084 J3084 | Gas | 641.8 MW | 2025 | 2026 |
| Malden BESS E0039 | Battery | 630.4 MW | 2025 | 2027 |
| Sullivan Generating Station 1 AB1-087 | Gas | 575 MW | 2015 | 2027 |
| Sullivan Generating Station 2 AB1-088 | Gas | 575 MW | 2015 | 2027 |
| Queue J3075 J3075 | Solar + Battery | 560 MW | 2022 | 2025 |
| Merom Station E0054 | Gas | 530 MW | 2025 | 2028 |
| Mitchell BESS E0033 | Battery | 526.7 MW | 2025 | 2028 |
| Queue LGE-GIS-2021-008susp. LGE-GIS-2021-008 | Solar + Battery | 500 MW | 2021 | 2026 |
| Queue J3232 J3232 | Gas | 500 MW | 2024 | 2028 |
| Queue J3931 J3931 | Solar | 500 MW | 2025 | 2030 |
| Queue J4005 J4005 | Gas | 500 MW | 2025 | 2028 |
| Queue J3331 J3331 | Gas | 470 MW | 2024 | 2028 |
| Queue J4021 J4021 | Gas | 470 MW | 2025 | 2028 |
| Queue AI1-022 AI1-022 | Battery | 450 MW | 2022 | 2026 |
| Dolphin Solar AG1-226 | Solar | 450 MW | 2020 | 2024 |
| Merom Storage APP-100245 | Solar + Battery | 405 MW | 2025 | 2028 |
| Queue J2496 J2496 | Battery | 400 MW | 2022 | 2026 |
| Queue AH2-257 AH2-257 | Solar | 400 MW | 2022 | 2024 |
| Queue AH2-352 AH2-352 | Solar | 400 MW | 2022 | 2026 |
| Queue J3666 J3666 | Gas | 378.8 MW | 2024 | 2028 |
| Queue J3942 J3942 | Solar | 365 MW | 2025 | 2030 |
| Queue AH2-413 AH2-413 | Solar + Battery | 365 MW | 2022 | 2026 |
| Queue AH2-414 AH2-414 | Battery | 350 MW | 2022 | 2026 |
| Queue J3943 J3943 | Solar | 337 MW | 2025 | 2030 |
| Brickyard Energy Storage E0021 | Battery | 310 MW | 2025 | 2028 |
| Queue J1058 J1058 | Solar | 300 MW | 2018 | 2024 |
| Queue J1308 J1308 | Solar | 300 MW | 2019 | 2024 |
| Queue J2215 J2215 | Battery | 300 MW | 2022 | 2024 |
| Queue J2270 J2270 | Solar | 300 MW | 2021 | 2024 |
| Queue J3114 J3114 | Solar + Battery | 300 MW | 2025 | 2026 |
| Queue J3834 J3834 | Battery | 300 MW | 2024 | 2026 |
| Queue J3910 J3910 | Wind | 300 MW | 2025 | 2030 |
| Queue J4063 J4063 | Wind | 300 MW | 2025 | 2030 |
| Mammoth Central Energy Center AF2-132 | Solar | 300 MW | 2020 | 2027 |
| Mammoth Central II Energy Center AG1-302 | Solar | 300 MW | 2020 | 2028 |
| Mammoth South Energy Center AF2-133 | Solar | 300 MW | 2020 | 2027 |
| Queue J1743 J1743 | Solar | 292.9 MW | 2022 | 2026 |
| Queue AI1-085 AI1-085 | Solar | 290 MW | 2022 | 2030 |
| Sandcut Storage APP-100248 | Solar + Battery | 279.7 MW | 2025 | 2028 |
| Queue J3564 J3564 | Wind | 275 MW | 2024 | 2028 |
| Queue J3846 J3846 | Wind | 275 MW | 2025 | 2030 |
| Madison County Combustion Turbine E0046 | Gas | 267.8 MW | 2025 | 2028 |
| Mayapple Solar AG1-349 | Solar | 260 MW | 2020 | 2027 |
| Vermilion Grove Wind AF1-204 | Wind | 255 MW | 2019 | 2022 |
| Queue J2581 J2581 | Battery | 250 MW | 2022 | 2026 |
| Queue J2970 J2970 | Solar | 250 MW | 2022 | 2026 |
| Queue J3077 J3077 | Solar + Battery | 250 MW | 2022 | 2026 |
| Queue J829 J829 | Solar | 250 MW | 2017 | 2022 |
| Southern Pike Solar LLC project AG2-029 | Solar | 250 MW | 2025 | 2024 |
| Dolphin Solar LLC project AG2-163 | Solar | 250 MW | 2025 | 2024 |
| Queue AH2-112 AH2-112 | Solar + Battery | 250 MW | 2022 | 2026 |
| Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2 R1011 | Solar + Battery | 250 MW | 2021 | 2024 |
| Queue J2849 J2849 | Solar | 245 MW | 2022 | 2025 |
| Queue J1067 J1067 | Solar | 240 MW | 2018 | 2023 |
| Queue J3495 J3495 | Solar | 220 MW | 2024 | 2028 |
| STARKE CENTRAL PROJECT, LLC project AG2-245 | Solar | 210 MW | 2025 | 2023 |
| Queue AH2-419 AH2-419 | Solar + Battery | 210 MW | 2022 | 2026 |
| Queue J1069 J1069 | Wind | 200 MW | 2018 | 2023 |
| Queue J1348 J1348 | Solar | 200 MW | 2019 | 2025 |
| Queue J1378 J1378 | Solar | 200 MW | 2019 | 2024 |
| Queue J1381 J1381 | Solar | 200 MW | 2019 | 2026 |
| Queue J1481 J1481 | Solar | 200 MW | 2019 | 2025 |
| Queue J1616 J1616 | Solar | 200 MW | 2020 | 2026 |
| Queue J1642 J1642 | Solar + Battery | 200 MW | 2022 | 2023 |
| Queue J1684 J1684 | Solar | 200 MW | 2023 | 2029 |
| Queue J1691 J1691 | Solar | 200 MW | 2020 | 2026 |
| Queue J1772 J1772 | Solar | 200 MW | 2020 | 2026 |
| Queue J1780 J1780 | Solar | 200 MW | 2020 | 2026 |
| Queue J1786 J1786 | Solar | 200 MW | 2020 | 2026 |
| Queue J2213 J2213 | Battery | 200 MW | 2022 | 2028 |
| Queue J2230 J2230 | Solar | 200 MW | 2022 | 2025 |
| Queue J2472 J2472 | Battery | 200 MW | 2022 | 2027 |
| Queue J2509 J2509 | Wind | 200 MW | 2022 | 2025 |
| Queue J2538 J2538 | Solar | 200 MW | 2025 | 2026 |
| Queue J2566 J2566 | Solar | 200 MW | 2022 | 2026 |
| Queue J2572 J2572 | Battery | 200 MW | 2022 | 2025 |
| Queue J2586 J2586 | Battery | 200 MW | 2022 | 2025 |
| Queue J2663 J2663 | Battery | 200 MW | 2022 | 2026 |
| Queue J2848 J2848 | Solar | 200 MW | 2025 | 2025 |
| Queue J2987 J2987 | Solar | 200 MW | 2022 | 2025 |
| Queue J3249 J3249 | Battery | 200 MW | 2024 | 2028 |
| Queue J3291 J3291 | Battery | 200 MW | 2024 | 2028 |
| Queue J3357 J3357 | Battery | 200 MW | 2024 | 2028 |
| Queue J3550 J3550 | Battery | 200 MW | 2024 | 2027 |
| Queue J3691 J3691 | Battery | 200 MW | 2024 | 2028 |
| Queue J3719 J3719 | Solar | 200 MW | 2024 | 2028 |
| Queue J3873 J3873 | Battery | 200 MW | 2024 | 2029 |
| Queue J3879 J3879 | Solar + Battery | 200 MW | 2024 | 2030 |
| Queue J3948 J3948 | Battery | 200 MW | 2025 | 2030 |
| Queue J3978 J3978 | Solar + Battery | 200 MW | 2025 | 2029 |
Showing the 100 largest of 300 projects by requested capacity.
See 207 operating plants in Indiana · Regions: MISO, PJM Interconnection, Non-ISO Southeast.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).