State queue · Ohio
Ohio interconnection queue
183 proposed generation and storage projects — 163 active and 20 suspended — are in Ohio's interconnection queue, primarily in the PJM Interconnection, totaling 19.75 GW of requested capacity. Solar leads with 11.56 GW.
183
Proposed projects
19.75 GW
Requested capacity
Solar
Largest resource type
2026
Median planned online year
Requested capacity by resource type
Solar 58.5%Gas 18.1%Solar + Battery 11.0%Battery 9.0%Wind 3.2%Other 0.2%
Proposed projects by resource type
Solar projects120 · 11.56 GWGas projects16 · 3.57 GWSolar + Battery projects21 · 2.17 GWBattery projects20 · 1.78 GW
Also in the queue (too few for a dedicated page): Wind (3), Other (3).
All proposed projects in Ohio
| Type | ||||
|---|---|---|---|---|
| Chestnut Run Energy LLC project AH1-680 | Gas | 1.30 GW | 2025 | — |
| Trumbull Energy Center AB1-105 | Gas | 940 MW | 2015 | 2026 |
| Queue AJ1-008 AJ1-008 | Solar + Battery | 800 MW | 2023 | 2028 |
| Troy Energy, LLC project AH1-711 | Gas | 408.2 MW | 2025 | — |
| West Lorain Power Plant 345 kV AG1-500 | Gas | 406.4 MW | 2020 | 2031 |
| Oak Run Solar Project AG1-125 | Solar | 400 MW | 2020 | 2030 |
| Oak Run Solar Project AG1-126 | Solar | 400 MW | 2020 | 2030 |
| Butterfly Meadows AG1-410 | Solar | 300 MW | 2020 | 2024 |
| Yellow Wood Solar Energy Center AE2-221 | Solar | 300 MW | 2019 | 2026 |
| Firelands Wind AC2-103 | Wind | 297.7 MW | 2017 | 2027 |
| Queue AI2-081 AI2-081 | Solar | 271 MW | 2023 | 2025 |
| Queue AI1-167 AI1-167 | Battery | 250 MW | 2022 | 2028 |
| Cadence Solar Energy Center AD2-093 | Solar | 240 MW | 2018 | 2026 |
| Furnace Solar, LLC project AH1-055 | Solar | 220 MW | 2025 | 2026 |
| Eastern Cottontail Solar AE2-048 | Solar | 220 MW | 2019 | 2028 |
| Fountain Point Solar AE1-092 | Solar | 206.6 MW | 2018 | 2021 |
| South Branch Solarsusp. AD1-070 | Solar | 205 MW | 2017 | 2025 |
| Energy Pastures Solar Project, LLC project AG2-082 | Solar | 200 MW | 2025 | 2024 |
| Oak Run Solar Project, LLC project AG2-104 | Solar | 200 MW | 2025 | 2025 |
| Wombat Solar LLC project AG2-329 | Battery | 200 MW | 2025 | 2024 |
| Energy Pastures Solar Project, LLC project AH1-580 | Solar | 200 MW | 2025 | 2025 |
| Queue AI1-103 AI1-103 | Solar | 200 MW | 2022 | 2029 |
| Queue AI1-168 AI1-168 | Wind | 200 MW | 2022 | 2027 |
| Flint Grid AF1-062 | Battery | 200 MW | 2019 | 2027 |
| Pleasant Prairie Solar Energy Center AE2-214 | Solar | 200 MW | 2019 | 2027 |
| CG Fulton County AF1-206 | Solar | 199 MW | 2019 | 2028 |
| Queue AH2-168 AH2-168 | Solar | 185 MW | 2022 | 2025 |
| Sloopy Solar Energy Center AE2-217 | Solar | 180 MW | 2019 | 2028 |
| Riverlake Energy, LLC project AH1-537 | Solar | 178.5 MW | 2025 | 2025 |
| Kingwood Solar AD1-140 | Solar | 175 MW | 2017 | 2026 |
| Queue AI2-028 AI2-028 | Solar | 160 MW | 2022 | 2026 |
| Springwater Solar AF1-228 | Solar | 155 MW | 2019 | 2027 |
| Queue AH2-228 AH2-228 | Battery | 150 MW | 2022 | 2026 |
| Queue AI1-100 AI1-100 | Solar + Battery | 150 MW | 2022 | 2025 |
| Queue AI2-035 AI2-035 | Solar | 150 MW | 2023 | 2027 |
| Harvey Solar I AD2-067 | Solar | 150 MW | 2018 | 2028 |
| Palomino Solar AG1-107 | Solar | 150 MW | 2020 | 2027 |
| Wild Grains Solar AF2-014 | Solar | 150 MW | 2019 | 2027 |
| Kensington Solarsusp. AE2-194 | Solar | 145 MW | 2019 | 2026 |
| Grover Hill Wind Project AE1-245 | Wind | 140.3 MW | 2018 | 2026 |
| Queue H037 H037 | Gas | 135 MW | 2008 | 2010 |
| Highland 3 Solar AF1-283 | Solar | 130 MW | 2019 | 2030 |
| South Branch Solar AF2-375 | Solar | 129.6 MW | 2020 | 2026 |
| Harvey Solar I AG1-034 | Solar | 127.5 MW | 2020 | 2029 |
| Vinton Solar AC1-194 | Solar | 125 MW | 2016 | 2027 |
| Queue AH2-345 AH2-345 | Solar | 120 MW | 2022 | 2025 |
| Queue AI1-074 AI1-074 | Solar + Battery | 120 MW | 2022 | 2027 |
| Border Basin AE1-146 | Solar | 120 MW | 2018 | 2026 |
| Canal Road AF2-187 | Solar | 120 MW | 2020 | 2027 |
| Tymochtee Solar AF1-229 | Solar | 120 MW | 2019 | 2026 |
| Sycamore Creek Solar AC2-015 | Solar | 117 MW | 2016 | 2025 |
| Queue AH2-264 AH2-264 | Solar | 115 MW | 2022 | 2026 |
| Appalachian Cottontail Solar AE2-136 | Solar | 114 MW | 2019 | 2028 |
| Green Camp Solar II AH1-542 | Solar + Battery | 110 MW | 2025 | 2025 |
| Strawhat Solar Energy Centersusp. AE1-091 | Solar | 110 MW | 2018 | 2026 |
| Union Ridge Solar AF2-122 | Solar | 107.7 MW | 2020 | 2026 |
| Queue AH2-010 AH2-010 | Solar | 100 MW | 2021 | 2024 |
| Queue AH2-068 AH2-068 | Solar | 100 MW | 2022 | 2027 |
| Queue AH2-126 AH2-126 | Battery | 100 MW | 2022 | 2026 |
| Queue AH2-217 AH2-217 | Battery | 100 MW | 2022 | 2026 |
| Queue AI1-190 AI1-190 | Solar + Battery | 100 MW | 2022 | 2027 |
| Queue AI2-328 AI2-328 | Solar | 100 MW | 2023 | 2026 |
| Queue AI2-329 AI2-329 | Solar | 100 MW | 2023 | 2026 |
| Butterfly Meadows AG1-411 | Battery | 100 MW | 2020 | 2024 |
| Clermont County Solar Projectsusp. AE2-318 | Solar | 100 MW | 2019 | 2025 |
| Marion County Solar Project AC2-195 | Solar | 100 MW | 2017 | 2025 |
| Nottingham Solarsusp. AE2-290 | Solar | 100 MW | 2019 | 2023 |
| Nuthatch Solar 5 AF1-282 | Solar | 100 MW | 2019 | 2030 |
| Scioto Solar AF1-285 | Solar + Battery | 100 MW | 2019 | 2026 |
| Queue AH2-155 AH2-155 | Solar | 95 MW | 2022 | 2025 |
| Blossom Solar AF2-150 | Solar | 88 MW | 2020 | 2027 |
| Queue AH2-146 AH2-146 | Solar + Battery | 87.2 MW | 2022 | 2027 |
| Queue AH2-164 AH2-164 | Solar | 85 MW | 2022 | 2026 |
| Queue AI1-112 AI1-112 | Solar + Battery | 85 MW | 2022 | 2026 |
| Harvey Solar I AG1-024 | Solar | 85 MW | 2020 | 2029 |
| Prairie Flyer Energy Storage AG1-207 | Battery | 85 MW | 2020 | 2028 |
| Queue AH2-374 AH2-374 | Battery | 84 MW | 2022 | 2027 |
| Carnation AF2-371 | Solar | 84 MW | 2020 | 2028 |
| Queue AI2-330 AI2-330 | Solar | 83.5 MW | 2023 | 2028 |
| Marion County Solar Project II, LLC project AG2-119 | Solar | 80 MW | 2025 | 2024 |
| Hamden Energy LLC project AG2-548 | Solar + Battery | 80 MW | 2025 | 2023 |
| Hamden Energy LLC project AG2-665 | Solar + Battery | 80 MW | 2025 | 2024 |
| Queue AH2-165 AH2-165 | Solar | 80 MW | 2022 | 2025 |
| Queue AH2-169 AH2-169 | Solar | 80 MW | 2022 | 2025 |
| Angelina Solar I AC2-111 | Solar | 80 MW | 2017 | 2027 |
| Frasier Solar AF2-149 | Solar | 80 MW | 2020 | 2028 |
| Hillclimber Solar AE2-305 | Solar | 78 MW | 2019 | 2029 |
| Queue AI2-164 AI2-164 | Solar | 72 MW | 2023 | 2025 |
| Queue AI2-029 AI2-029 | Solar | 70 MW | 2022 | 2026 |
| Queue AJ1-023 AJ1-023 | Gas | 70 MW | 2023 | 2024 |
| Circleville Solar Energysusp. AC2-029 | Solar | 70 MW | 2017 | 2027 |
| Dixon Solar AC1-188 | Solar | 70 MW | 2016 | 2028 |
| Dixon Solar AF2-048 | Solar | 70 MW | 2019 | 2028 |
| South Field Energy LLC project AH1-699 | Gas | 69 MW | 2025 | — |
| Queue AH2-106 AH2-106 | Gas | 69 MW | 2022 | 2022 |
| Chinchilla Solar LLC project AG2-289 | Battery | 66.6 MW | 2025 | 2024 |
| Morrow County Solar IIsusp. AF1-122 | Solar | 64 MW | 2019 | 2026 |
| Queue AI2-024 AI2-024 | Solar | 60 MW | 2022 | 2028 |
| Chestnut Solarsusp. AD1-106 | Solar | 60 MW | 2017 | 2026 |
| Mark Center Solar Project AE2-322 | Solar | 60 MW | 2019 | 2026 |
Showing the 100 largest of 183 projects by requested capacity.
See 199 operating plants in Ohio · Regions: PJM Interconnection, MISO.
Source: "Queued Up" (Rand et al., Lawrence Berkeley National Laboratory, 2026 edition) (data as of December 31, 2025).