Trenton Solar Power Plant

A 74.9 MW solar power plant in Gilchrist, Florida, owned by Duke Energy Florida, LLC, commissioned in 2019.

Facility nameplate · EIA Plant ID 62543Solar
Nameplate capacity
74.9 MW
Primary fuel
Solar
Commissioned
2019
Time in queue (20162019)
3 yrs
Owner
Duke Energy Florida, LLC
Location
Gilchrist, Florida
Generation (2024)
145.1 GWh
Status
Operating
Technology
Solar Photovoltaic
Units
1

This facility was matched to a Non-ISO Southeast interconnection request (LBNL Queued Up): queued 2016, commercial operation 2019 3 years in the queue. See the Southeast queue or typical durations.

Reported annual generation

YearGWh
20193.3
2020169.8
2021161.7
2022165.5
2023140.9
2024145.1

Nearby power plants

PlantFuelCapacityDistance
TrentonStorage11 MW~4 km
Bell Ridge SolarSolar74.5 MW~16 km
Hardeetown Solar Power PlantSolar74.9 MW~17 km
Gilchrist County SolarSolar74.5 MW~17 km
County Line Renewable Energy CenterSolar74.9 MW~25 km
High Springs Solar Power PlantSolar74.9 MW~28 km

See all solar plants in Florida or browse all plants in Florida.